Create a Potential Change Order (PCO)
Creating a potential change order (PCO) is the beginning of the change process in BIM 360 cost management. This tutorial demonstrates how to create a PCO for a project.
Before You Begin
- Register an app
- Acquire a 3-legged OAuth token with the
data:writescope. - Verify that you have access to the relevant BIM 360 account and BIM 360 project.
- Retrieve the project ID for your project. To obtain a project ID, use GET projects.
Step 1: Create a PCO
Use the container ID you retrieved in the first tutorial (be00f32e-c03c-4c7b-9ec4-d2614bf1980c in this example) to call POST change-orders/pco.
Request
Response
This example returns the PCO ID f5c7869f-faa1-4418-b8e6-e7c23c495560. You can use a PCO ID later to get the latest status of the PCO. For example, for this ID you would call GET change-orders/pco/f5c7869f-faa1-4418-b8e6-e7c23c495560.
Step 2: Create a Cost Item
You can create cost items to break down change if necessary. Use the container ID you used before (be00f32e-c03c-4c7b-9ec4-d2614bf1980c) and the PCO ID you just retrieved (f5c7869f-faa1-4418-b8e6-e7c23c495560) to call POST cost-items.
Request
Response
To create more cost items for this PCO, repeat step 2.
Congratulations! You have created a PCO with a cost item in BIM 360 cost management. A cost engineer can use this to start the change process in cost management. It allows you to estimate, quote and review the changes. Later you can call GET change-orders/pco/f5c7869f-faa1-4418-b8e6-e7c23c495560 to get the latest status and cost(estimated, proposed, submitted, approved, committed) of this change.